From Day-Ahead to Final Schedule: How Spain’s Generation Mix Changes
A seven-year comparison of Spain’s base programme and final operating schedule, by technology and hour.
Alexandre Danthine · AAG AdvisorsHow much does Spain's generation mix change between the day-ahead base programme and the final schedule?
Models of the Spanish power market often take the day-ahead result as a settled picture of the next day. The note shows that this result is only a starting point. Network limits, intraday trading, outages, balancing and new forecasts keep changing the output assigned to each technology until and during delivery. The note measures how large these changes are over seven years, by technology and by hour.
It compares the base programme (PDBF: the day-ahead result plus physical bilateral contracts) with the closed final schedule (P48CIERRE). The gap shows the joint effect of all later processes without assigning each change to one of them, and it remains a schedule rather than metered output. Gross revisions in both directions more than double between 2019 and 2025, from 35.5 TWh to 73.7 TWh. In 2025, each 100 MWh in the base programme sees 29 MWh of movement in both directions, or about 14 MWh counting one side only. The net change stays small because technologies offset one another.

In the full article
- When in the day schedule changes are largest, with a focus on the evening ramp
- A day when CCGT output rises from zero in the base programme to 126.4 GWh in the final schedule
- The technologies behind the 73.7 TWh of gross two-way revisions
- How persistent the revisions are from month to month, and the implications for batteries, flexible demand and renewable plants
The complete analysis, charts and data are on Substack. Paid subscribers get every article in full, plus the monthly market reports.