Green compute is the new green hydrogen
The Spanish government attempt to kill the infrastructure of the future
Alexandre Danthine · AAG AdvisorsI could have called this article “The death of the Spanish data center economy,” but that might have been a bit too harsh, since the regulation I’ll discuss is still under consultation.
If you are in the Spanish market, you have certainly heard about the public consultation on data centers published at the end of August 2026 and closing on the 10th of September. Newspaper headlines highlighted that the government wanted to require 80% renewable generation for projects to receive grid connection.
If the headline is true, the details are even stricter and similar to what the first proposal for green hydrogen labeling put forward. To me, it contradicts what the renewables industry and the grid need.
Please find the list of points pushed by the governments; I’ll discuss them afterward:
If you are an investor, how many red flags did you spot?
Challenge of the proposal
The 80% hourly matching requirement is where the proposal becomes problematic. It is not an annual or monthly renewable target: the compliance must be demonstrated hour by hour.
For a 100 MW data center, it means securing baseload PPAs covering 80MW in every hour. In practice, it requires a carefully structured mix of solar, wind and battery storage. It is possible, but complex and expensive. The likely outcome is not more competition, but the opposite: a market increasingly dominated by large utilities and sophisticated energy players able to structure these complex products.
The 10-year minimum PPA duration adds another constraint, which was not present in green hydrogen. Forcing the structuring of such products for the next 10 years will be complex and costly, considering that it may never have been done in the peninsula.
Something investors hate, but Spanish governments apparently love, is applying retroactive regulatory changes. Some developers have already taken the risk, secured a grid connection, and built their business case under the current regulations. Changing the rules midway might let them invest in a country with less regulatory risk.
Finally, the special regime above 90% renewable seems like a far-away mirage. As the Spanish government just extended part of the nuclear fleet to 2030, it is highly unlikely to reach this threshold anytime soon.
Alternative to the proposal
Considering all that, do I preach letting data centers connect wherever they want, even if that ultimately requires building new gas turbines, as we see in the US?
No.
However, Spain is wasting a good opportunity here. Indeed, the renewable sector has been waiting for demand to grow for years to cope with increasing cannibalization.
What's missing from this proposal is location.
Unless renewables are co-located with data centers, location isn't part of the equation. Data centers placed in the right location could drastically reduce grid operating costs (a technical restriction) that have been skyrocketing in recent years.
One proposal is to incentivize data centers to locate near curtailment zones. You can find some information in this article.
One way to enforce that is a locational grid fee that would incentivize demand connection where demand is low and renewable curtailment is high, while connections near Madrid or other major population centers would have higher grid fees. France (TURPE) and the UK (TNUoS) have implemented similar market designs in which grid fees vary by location, and many other European countries have similar alternatives.
On another point raised by the Spanish government, peak-demand stress could be managed through flexible grid connections by requiring data centers to shut down during the few hundred hours when the grid is under stress.
Conclusion
Hopefully, green cloud will not become the new green hydrogen: hydrogen started with extremely strict rules that were later relaxed once their practical impact became clear. For data centers, the risk of scaring investors away may be even greater, because their demand is far more concrete and projects can be relocated elsewhere on the grid much more easily than hydrogen production.
Keeping data center build-out in check is essential, and implementing regulations is necessary as power demand grows significantly. However, those rules should focus on data center location and guardrails to prevent huge load increases during peak periods rather than forcing insensible hourly renewable targets.
The time for renewable-only requirements is gone, and the grid should be a priority.
Looking forward to hearing your thoughts!