2025: The Year Grid Took Center Stage in Spain

From the April blackout to emergency measures, 2025 marked the year physics finally caught up with market design in the Spanish electricity system

Alexandre Danthine · AAG Advisors

Grid infrastructure rarely makes headlines. Markets, prices, policies - yes. But the physical wires and transformers that actually move electrons? They tend to stay in the background.

In Spain, 2025 was the year the grid demanded attention. The April 28th blackout, emergency voltage measures in October, and congestion costs exceeding 3.7 billion euros forced a conversation that had been growing for years.

This article will not revisit the blackout itself or its causes. Instead, I want to walk through what the data tells us about how Spain’s grid operated in 2025, what changed, and what to expect next.

The Cost Explosion

Let’s start with the big picture. The graph below shows the cumulative cost of congestion management in Spain from 2018 to 2025.

The trajectory is striking. In 2019, total costs were around 250 million euros. By 2025, they exceeded 3.7 billion euros. That’s roughly a 15-fold increase in six years.

What’s particularly notable is the acceleration from 2022. The 2025 line (in red) sits dramatically above all previous years, and the gap only widened as the year progressed.

Let’s break this down by month to see where the costs accumulated.

While the increase till 2025 has already been commented in my first article, note the massive spike in May 2025, the month immediately following the blackout. Day-ahead and real-time costs combined exceeded 450 million euros in a single month. On May 1st alone, two days after the blackout, approximately 120 GWh was redispatched through technical restrictions. To put that in perspective, the Spanish system produces around 600 GWh per day, meaning more than 20% of the electricity allocated in the day-ahead market was redispatched that day.

Another notable pattern in 2025 is the shift after October’s emergency measures. Real-time costs (the lighter bars) decreased toward year-end as volumes shifted to the day-ahead timeframe. I’ll explain why in the real-time section below.

Day-Ahead Technical Restrictions

The day-ahead technical restrictions market has two phases. Phase 1 is where REE solves congestion, voltage, and other security issues identified after the day-ahead market clears. Phase 2 rebalances the energy gap created by Phase 1. For a detailed explanation of how these mechanisms work, see my previous article.

Let’s look at Phase 1 by technology and by reason.

The upward side (positive values) is dominated by Gas CCGT (gray) and Nuclear (red). These are the technologies called upon to increase production for grid security. The massive spikes in April and May reflect the post-blackout period when operators ramped up conventional generation for stability.

The downward side (negative values) tells a different story. This is curtailment, generators forced to reduce output. Solar PV (green) and wind (light blue) bear the brunt, particularly during summer months when renewable production is highest.

Here’s the critical point: Phase 1 downward actions are not compensated. When a renewable generator is curtailed in Phase 1, they lose their day-ahead revenue entirely. Their position is cancelled, and they receive nothing in return. This is a fundamental issue for renewable business models, one I explored in detail in my article [Half a Billion on the Line], where I calculated that Spanish generators lost 561 million euros to uncompensated curtailment between 2020 and 2025.

Now let’s examine the reasons for these restrictions.

Voltage control (pink/red) emerged as the dominant driver in 2025, particularly after the blackout. For the electrical engineers among my readers, it may seem surprising to see voltage control expressed in MWh rather than MVAr, but in Spain’s technical restrictions framework, this is how the TSO manages reactive power needs.

Congestion (both basecase N-0 in dark green and contingency N-1 in light green) remains a persistent issue. Basecase congestion is particularly worrying—it means the system is operating at its limits even under normal conditions, not just during equipment outages.

Insufficient Upwards Reserve started after the set-up of the Urgent Measures to Stabilize Voltage, starting last October, see my article on the subject.

One of the most telling charts from 2025 shows the divergence between day-ahead market prices and technical restriction prices.

The blue line represents day-ahead (spot) prices, which collapsed in April and May, dropping below 50 €/MWh amid high renewable production. The red line shows the average price paid for upward Phase 1 restrictions, which remained stubbornly high around 150-175 €/MWh throughout the year.

This divergence tells the real story. While the market signaled abundant, cheap energy, the grid required expensive interventions to actually deliver it safely. A single national clearing price masks growing local bottlenecks.

Phase 2: The Rebalancing Act

After Phase 1 creates an energy imbalance (calling up some units, curtailing others), Phase 2 must close the gap. Let’s see which technologies participate.

Wind (light blue) and Solar PV (green) now represent more than 50% of Phase 2 energy. This market functions almost like an additional intraday gate, through which renewable generators can bid to fill the gap created by Phase 1. Unlike Phase 1 down, Phase 2 is remunerated on a pay-as-bid basis, so participating generators earn revenue.

Real-Time Technical Restrictions: Where Things Get Interesting

Real-time technical restrictions are the last-minute adjustments to ensure system security. Unlike day-ahead Phase 1, generators in real-time can bid prices for downward actions and this created a fascinating market dynamic in 2025.

The upward side shows Gas CCGT (gray) dominating, with volumes highest in the first half of the year. The blackout is marked with a red dotted line—note the immediate spike in interventions afterward as operators took no chances with system stability.

But look at what happens from October onwards. Upward real-time volumes decreased significantly. Why? Because the emergency measures implemented on October 21st shifted much of this work to the day-ahead timeframe. Insufficient upward reserve, previously a major real-time concern, is now addressed earlier.

Let’s examine the reasons more closely.

Insufficient Upward Reserve (light blue) was the dominant reason before October’s measures. This refers to situations in which the system lacked quickly deployable generation capacity to cover potential shortfalls, a serious security concern. After the October measures (which required certain plants to stay online and improved secondary reserve discipline), these volumes dropped substantially.

Congestion (dark and light green) remained relatively constant throughout the year. Basecase congestion appearing in real-time is particularly concerning; it suggests the system is frequently operating near its limits.

The Negative Price Revolution

Here’s where 2025 gets really interesting. In July 2024, regulation BOE-A-2024-11959 legalized negative bidding in the real-time technical restrictions market when day-ahead prices fell below 1 €/MWh. The impact became visible throughout 2025.

Solar PV (green) and wind (blue) are now bidding heavily negative for downward curtailment, sometimes reaching -300 to -600 €/MWh. What does this mean? When a generator bids -200 €/MWh for curtailment, they’re saying: “Pay me 200 euros for each MWh I don’t produce, and I’ll gladly reduce output.”

This reverses the cost dynamic. Before this regulation, the downward real-time market had positive prices; generators paid the TSO for the privilege of reducing output. Now, the TSO pays generators. In July 2025 alone, this cost reversal amounted to approximately 22.7 million euros paid to curtailed generators.

I explored this phenomenon in detail in my article [When Not Producing Pays: The Paradox of Curtailment Revenues]. The key insight: real-time curtailment has become profitable, while day-ahead curtailment remains uncompensated. This creates a strategic incentive for generators to avoid day-ahead commitments and instead capture value in real time.

What to Expect in 2026

The trends from 2025 point to several developments we should watch in 2026:

  1. Voltage control market launch. A dedicated market for voltage services is expected in early 2026, which should separate reactive power needs from the technical restrictions framework. This could improve price signals and efficiency.

  2. Battery storage deployment. Spain has approximately 30 GW of battery storage in its development pipeline. As these assets come online, they’ll provide fast-responding flexibility that could reduce reliance on gas turbines for upward regulation. But batteries will also participate in curtailment, potentially intensifying competition in the real-time downward market.

  3. Continued renewable growth. More solar and wind capacity means more potential for congestion and curtailment. Without proportional grid investment, technical restriction costs will likely continue to rise.

  4. The compensation question. The EU Clean Energy Package (Article 13.7) requires that curtailment be compensated except in specific circumstances. Spain’s approach, in which day-ahead Phase 1 downward actions go uncompensated, seems difficult to justify legally.

The fundamental question remains: How can Spain break the cycle of rising grid costs? More transmission investment would help, but it takes years to build. Better locational signals could direct new renewable capacity to less congested areas. Faster battery deployment would add flexibility.

Cheers,

Alexandre

First published on Substack · 13 February 2026

Get the next article by email. A new article on European power markets every other week, from the bid curve to the order book.

More Articles

Latest articles

All 39 articles, free ones in full and subscriber articles in summary.

AAG Contact

Questions on a market?

Book a 30-minute introductory call. Tell us about your project and your timeline, and we will see whether AAG is the right fit.